Europe
: The cost of building 3G networks can be cut by 30 per cent –
a figure that could save a network operator £300million, according
to UK-based 3G optimisation specialists Arieso.
Inset
is Shirin Dehghan CEO of Arieso.
Arieso
identified the cost saving, which could further grow as the network
grows, with figures taken from network trials carried out using Arieso’s
advanced optimising techniques. In one best case scenario, Arieso
determined a potential saving of over 40 per cent, with nearly half
of the original sites installed by the operator found to be unnecessary.
The reduced size network showed no loss of service or reduction of
key performance indicators.
However,
if the operator chooses to keep the original number of sites, the
capacity of the optimised network can be doubled, the coverage improved,
and the number of dropped calls reduced.
3G networks
require a radically different approach to that of existing 2G and
2.5G networks. Operator foresight and optimisation is now proving
critical in terms of developing the highest quality network in the
most cost-effective manner.
Arieso’s
trials use intelligent network optimisation techniques based on operator
data. The multimedia composition of 3G network traffic requires a
much more sophisticated approach to implementing coverage and capacity
to meet subscriber expectations.
Arieso
chairman Mike Pinches explained: “Taking the UK as a ‘typical’
scenario, a network of around 10,000 sites would be required for national
coverage. The average cost of a site is £100K including the
building, radio and ancillary services, installation and commissioning,
giving an investment of £1 billion.
“If
the network is properly optimised prior to implementation, our trial
results see an average saving of £300 million. If an existing
network is optimised using the correct intelligent products, then
sites proved to be ‘surplus’ to existing requirements
can be used to provide extra capacity.”